Main Ditch Updates and Documents

Print
Press Enter to show all options, press Tab go to next option

Public Documents, Materials, and Information

This page is dedicated to documents and information related to the Upper Main Ditch Piping Project. To receive an email when information is posted to this page, please sign up for eNews, select the Main Ditch Project categories under News and Calendar headings.

Visit the Upper Main Ditch Project main webpage for background and other ways to stay informed about this project.

2019 Updates

January 25, 2019
Please see the Notice and Final Environmental Impact Report (FEIR) documents below. The FEIR document is large and may take time to download. We recommend saving the documents to your own device for better accessibility. These documents are also posted to the  Main Ditch Updates and Documents webpage.

 

Notice - Final Environmental Impact Report (FEIR) Available for Review

 Final Environmental Impact Report (FEIR) (85 MB)

For your convenience we are including below the Draft Environmental Impact Report (DEIR) and its appendices. These files have been broken down into smaller files for accessibility purposes but many are still very large files, we recommend saving the documents to your own device for better accessibility.

Cover Executive Summary & Introduction - Sections ES-01 (8 MB)
Project Description - Section 02 (91 MB)
Environmental Impact - Section 03 (51 MB)
Reference & Other - Sections 04-07 (1 MB)

Appendix A (39 MB)
Appendix B - Sections 1-7 (111 MB)
Appendix B - Section 8-9 (43 MB)
Appendix C (42 MB)
Appendix D (13 MB)
Appendix E (60 MB)

Background information is posted on the Upper Main Ditch Piping Project main webpage.
Board action items are contained here: Main Ditch Piping Project - Board Action.

2018 Updates

September 28, 2018

 Updated Projected Project Schedule - September 28, 2018

Task Projected Date
 

Final Environmental Impact Report (EIR)
Certification and Project Approval

 

December 2018/January 2019

 

Construction

 

2019-2020

  

 August 29, 2018

An information item was presented at the District's August 27 regular Board meeting.

8/27/18 - Regular Board Meeting II #4, Page 30

August 17, 2018

At its August 13 regular meeting, the District's Board of Directors voted to provide an additional 30-day public comment period on the DEIR.

Beginning: Monday, August 20 , 2018

Ending: Tuesday, September 18, 2018

Previously submitted comments: DO NOT NEED TO BE RESUBMITTED

NOTICE OF ADDITIONAL 30-DAY PUBLIC COMMENT PERIOD

 June 22, 2018

Public Meeting on the DEIR  June 27, 2018 at 6:00 p.m.
Pollock Pines-Camino Community Center, 2675 Sanders Dr., Pollock Pines      

Summary and Overview Sheet
Handout for Meeting

Comment Form

Ways to Stay Informed
and Provide Feedback

 

June 11, 2018

Please note that because of the large size of the DEIR posted on June 6, we have broken it down into smaller sections. There are still several sections that are large. Section 2 is 91 megabytes (MB) alone. The entire DEIR is almost 150 MB. The files will take time to download. Some computer systems may time out, we suggest right clicking on the link and choosing "Save As" to save to your own device for better access.

Main Ditch DEIR
Cover, Executive
Summary, & Introduction
Sections ES - 01
(8 MB)

Main Ditch DEIR
Project Description
Section 02
(91 MB)
Main Ditch DEIR
Environmental Impact
Section 03
(51 MB)
Main Ditch DEIR
References & Other
Sections 04 - 07
(1 MB)

 

June 6, 2018

Notice of Availability and Public Meeting Scheduled (NOA) (100 KB)

Draft Environmental Impact Report (DEIR) (150 MB)

Appendix A (39 MB)

Appendix B - Sections 1-7 (111 MB)

 Appendix B- Sections 8-9 (43 MB)

Appendix C (42 MB)

Appendix D (13 MB)

 Appendix E (60 MB)

 

 Updated Projected Project Schedule - June 6, 2018

Task Projected Date
 

Final Environmental Impact Report (EIR)
Certification and Project Approval

 

Summer/Fall 2018

 

Construction Contract Award

 

Summer/Fall 2018

 

Construction – Phase I

 

Fall 2018 - Winter 2019

 

Construction – Phase 2

 

Fall 2019 – Winter 2020

  

2017 Updates

June 28, 2017

Below is an updated projected project schedule.

Task Projected Date

Draft Environmental Impact Report (EIR)
release for public review

 Fall 2017
 

Final Environmental Impact Report (EIR)
Certification and Project Approval

 

Early 2018

 

Construction Contract Award

 

Summer 2018

 

Construction – Phase I

 

Fall 2018 - Winter 2019

 

Construction – Phase 2

 

Fall 2019 – Winter 2020

 

 

 

 

 

 

 

 

 

 

January , 2017

Upper Main Ditch Piping Will Protect Water Quality (January/February Waterfront)

2016 Updates

October 6, 2016

A Board Action webpage has been developed with the Agenda Item Summary's (AIS') and Board meeting minutes that relate to the Main Ditch Project No. 11032.

September 23, 2016 

Below is the projected project schedule.

Task Projected Date

Draft Environmental Impact Report (EIR)
release for public review

 Early November 2016
 

Final Environmental Impact Report (EIR)
Certification and Project Approval

 

Late February 2017

 

Construction Contract Award

 

Summer 2017

 

Construction – Phase I

 

Fall 2017 - Winter 2018

 

Construction – Phase 2

 

Fall 2018 – Winter 2019

 

 

 

 

 

 

 

 

 

 

August 26, 2016

Please see our news release Piping Project Gets Million-Dollar Federal Grant.

 May 23, 2016 - Update

The tentative survey schedule has been updated.

   
 TENTATIVE SCHEDULE

Survey No.

Day

Night

One

NA

4/28

Two

 NA

5/10

Three

 NA

5/26

Four

6/14

6/14

Five

6/22

6/22

Six

7/11

7/11

 

 

 

 

 

 

 

 

 April 21, 2016 - Update

Biological surveys will be taking place over the next four months within the District's easements located along the Upper Main Ditch. A letter, dated April 19 was mailed to the property owners adjacent to the Project area. The surveys will provide necessary information on biological resources in support of the environmental review and permitting processes for the piping project. These surveys will take place mostly at night and some days.

Night survey work is necessary to ensure the District is meeting federal and state environmental regulatory review requirements to accurately identify what biological species are present within the Project area.

Additional notifications will be made to adjacent residences prior to the start of each nighttime survey by  automated phone messages to known phone numbers along with door hangers of each residence.

Please contact the District and reference the Upper Main Ditch Project if you should have any questions at (530) 622-4513.


2015 Updates

December 1, 2015 - Update 

Since the June 29, 2015 Public Scoping Meeting, the District has been working on an alternative alignment evaluation for the Upper Main Ditch Piping Project. A draft 30% level design for Alignment 1 (Existing Ditch Alignment)  and Alignment 2 (Existing Ditch Alignment and Blair Road) has been completed. The 30% design further evaluates water handling during construction, storm water drainage improvements, ditch seepage, long term maintenance costs and construction costs for each alignment. The probable cost of the two alignments is estimated to be significantly higher than the original 10% design level cost estimate. A key factor in determining the preferred alignment, estimated construction costs are being peer reviewed by an independent consulting firm before a preferred project is selected and  preparation of the Draft Environmental Impact Report (EIR) begins.  Percolation/permeability testing and modeling is also currently being completed to supplement water loss data.

Although the schedule presented at the Public Scoping Meeting anticipated a Draft Environmental Impact Report (EIR) would be available January 2016 for public review, the District’s careful consideration of cost and other project considerations has delayed the EIR schedule by at least 5 months.

If you have additional questions regarding the Project, please contact the District at (530) 622-4513.

 September 2, 2015 - Update

The District has been awarded a Department of Water Resources drought grant in the amount of $1,007,500 for piping the ditch. In June, EID retained the services of a design engineering consultant to complete design on one of three alignments that are being considered for the piping project.

An Initial Study was completed and a Notice of Preparation of an environmental impact report (EIR) was released in June kicking off the environmental review process

A public scoping meeting was held On June 29, a public scoping meeting was held where the community and others had an opportunity to discuss any concerns they would like to see addressed in the EIR.

Completion of the Draft EIR is expected early in 2016 at which time public comment will be invited on the document Construction is expected to begin Fall 2016.

NOTE: This update was also published in the September/October 2015 addition of The Waterfront.

 Notice of Preparation (NOP) and Public Scoping Meeting

Initial Study (IS)

Initial Study Comment Form (Due by 5:00 p.m. on Thursday, July 16, 2015)

Scoping Meeting (June 29, 2015 calendar item)

Scoping Meeting FAQs

Ways to Stay Informed